New Capital City Amaravati will soon have temporary Secretariat complex and the work is going on at a rapid pace. Contractors are hopeful of completing works as per deadline set by Government.


The construction works started on February 17th and after completion of 100 days, the contractors L & T Constructions and Shapoorji and Pallonji started construction of rooms in five blocks of the temporary Secretariat complex. Contractors bagged this temporary Secretariat complex at a contract for Rs.201 Crores.


Death of Two workers during construction works initially stopped the works and it also grabbed media attention. But engineers of this contract companies have assured that the works will be done by June 15th. Right now, the construction of walls of the rooms and halls is under progress.


Soon they will start all the flooring works and then carpenter works, plumbing works will also follow them. Finally Electrical Wiring works and Interior decorations will be completed on ten days time. The slab works of the third and fourth blocks would be completed by June 5th.



మరింత సమాచారం తెలుసుకోండి: